Method — Assumption-based estimate
Points per system is a declared reference assumption. It sizes the T&C effort and instrument hire; it is not a specification or a commissioning schedule.
Every result below is produced by the same engineering engine that feeds the High-Rise reference project, so a quantity taken from this page and a quantity taken from the workflow cannot disagree.
Governing Formula
N_points = n_systems x n_points_per_system Where:
-
n= Number of systems
Derived Equations:
d_comm = n_systems x days_per_system N_instr = n_systems x instr_per_system Assumptions & Limitations
- No witness/hold-point schedule, no ITP and no manufacturer-specific requirement list.
- Assumes parallel resourcing across systems; sequential working extends the programme.