High-rise reference building under construction — 30 storeys above grade with 3 basement levels

Reference Real-Estate Development Project

High-Rise — 182 units · 11,250 m² sellable

A connected development projection: scope → engineering engines → quantities → BOQ → rates → cost → schedule → cash flow → financing → sales → profit. This page, the professional report, the PDF and the export package are all projections of one model object.

Total GFA
19,800 m²
Construction cost
EUR 16,122,379.38
Total dev. cost
EUR 28,485,270.38
Revenue
EUR 35,357,500.00
Profit
EUR 6,872,229.62

Showing the demonstration bundle. Load the High-Rise example in the Construction Workflow to edit rates — this page then follows your edits.

Project lifecycle & engineering map

Select any stage for its model-derived detail. Depth of engineering is stated per stage and never inferred from the presence of a material.

  • Complete
  • Engineering-modelled
  • Connected
  • Screening-level
  • Assumption-only
  • Partial
  • Not modelled
  • Not applicable

Land & project development

Assumption-only
Site area
2,400 m²
Footprint
600 m²
Site coverage
25.0%
FAR
8.25
Land cost
EUR 4,440,000.00
Land price / m²
EUR 1,850.00/m²

Domains behind this stage

  • Land & site Assumption-only 2400 m² land — entered as a market/site assumption

Land & site: Land area and site coverage are declared inputs; no survey or cadastral model exists.

Engineering coverage matrix

Depth answers how deep is the engineering?; the four flags answer what is wired downstream? A connected screening-level discipline stays labelled screening-level.

Domain Depth Qty BOQ Cost Report Detail
Land & site Assumption-only ✕ ✕ ✓ ✓ 2400 m² land — entered as a market/site assumption
Survey & geotechnical Not modelled ✕ ✕ ✕ ✓ No borehole log, no soil model, no foundation recommendation
Development feasibility Connected ✕ ✕ ✓ ✓ Construction cost separated from land, development costs and financing
Areas & unit program Connected ✕ ✕ ✕ ✓ Above-grade GFA, basement GFA, total GFA, sellable, common and service/core areas
Architecture — unit program Partial ✓ ✓ ✓ ✓ Unit types, distribution and areas are modelled; there is no floor plan, layout or circulation geometry
Earthworks & excavation Engineering-modelled ✕ ✕ ✕ ✓ Bulk cut with swell, fill and compaction
Substructure & basement Engineering-modelled ✕ ✕ ✕ ✓ Base slab, retaining walls, basement columns, grade beams, ramp, tanking and sumps
Structural frame Engineering-modelled ✓ ✓ ✓ ✓ Footings, columns, beams, core/shear walls, stairs, slabs, reinforcement and formwork
Envelope, facade & roofing Screening-level ✓ ✓ ✓ ✓ Curtain wall glazing, opaque facade panels, parapet and roof membrane
Electrical — supply & distribution Screening-level ✓ ✓ ✓ ✓ Connected load, diversity, max demand, transformer, generator, switchboards, cable, DBs, MCBs, luminaires
Plumbing & drainage Screening-level ✓ ✓ ✓ ✓ Water demand, storage, booster set, hot water, drainage and external stormwater
Mechanical — HVAC Screening-level ✓ ✓ ✓ ✓ Air volume, cooling load, AHUs, ductwork and diffusers
Fire & life safety Screening-level ✓ ✓ ✓ ✓ Occupant load, sprinklers, risers, hydrants, extinguishers, alarm, pumps, tanks, rated doors, escape stairs
Vertical transportation Screening-level ✓ ✓ ✓ ✓ Lift group sized on population and handling interval, plus shaft construction
Site & external works Engineering-modelled ✓ ✓ ✓ ✓ Paving, drainage, landscaping, fencing and external lighting
Quantity engine Connected ✓ ✓ ✓ ✓ 20 calculators, 50 consolidated materials, 0 fabricated records
Bill of quantities Connected ✓ ✓ ✓ ✓ 50 items, 50 flagged needs-review
Rate model Connected ✕ ✓ ✓ ✓ 100% of priced items carry an explicit rate source
Construction cost Connected ✕ ✓ ✓ ✓ EUR 16,122,379.38 — Σ(BOQ quantity × canonical rate)
Construction schedule Connected ✓ ✓ ✕ ✓ 50 activities from quantities × productivity
Resources & labour Assumption-only ✕ ✕ ✕ ✓ Crew size and daily outputs are editable productivity assumptions
Procurement Connected ✓ ✓ ✕ ✓ 15 packages, 100% of items on schedule dates
Cash flow Connected ✕ ✕ ✓ ✓ Monthly curve derived from cost × schedule
Financing Connected ✕ ✕ ✓ ✓ Loan drawdowns follow the cash-flow curve
Testing & commissioning Screening-level ✓ ✓ ✓ ✓ Test points, instruments and commissioning days
Handover Not modelled ✕ ✕ ✕ ✓ Not modelled — no snagging, as-built, O&M or asset register
Operation & OPEX Not modelled ✕ ✕ ✕ ✓ Not modelled — there is no OPEX, rent roll, facilities or asset-management model
Sales & revenue Connected ✕ ✕ ✕ ✓ 100% of unit types priced
Developer profitability Connected ✕ ✕ ✕ ✓ Profit = revenue − TDC, with margin, return on cost and break-even
Scenario engine Connected ✕ ✕ ✕ ✓ Base / downside / upside recomputed from the one model

Project definition, site & area model

Above-ground and basement area are named and separated everywhere. Total GFA is their sum and is never used as a synonym for above-grade area.

ParameterValueStatus
Storeys above grade30input
Basement levels3input
Total levels33derived
Typical footprint600 m²input
Building perimeter108.4 mderived
Building height96.0 mderived
Site area2,400 m²input
Land price / m²EUR 1,850.00/m²market assumption
Site coverage25.0%derived
Floor area ratio8.25derived
CurrencyEURinput
AreaValueBasis
Above-ground GFA 18,000 m² 30 storeys × 600 m² footprint
Basement GFA 1,800 m² 3 basement levels × 600 m² footprint
Total GFA 19,800 m² 18000 m² above grade + 1800 m² basement = 19800 m² over 33 levels
Sellable residential area 11,250 m² Σ unit types × units × unit area
Parking area 1,800 m² 50 spaces × 36 m² per space (assumption, incl. aisles and ramps)
Service & core area 2,376 m² 12% of total GFA for cores, lifts, stairs, corridors and plant (assumption)
Common & circulation area 4,374 m² Total GFA − sellable − parking − service & core
Non-sellable area 8,550 m² Total GFA − sellable residential

Unit program

TypeUnitsm²Sellable
Studio 60 35 2,100
1 Bedroom 60 55 3,300
2 Bedroom 30 80 2,400
3 Bedroom 30 105 3,150
Penthouse 2 150 300
Total 182 11,250

Feasibility, construction cost & development cost

Construction cost is Σ(BOQ quantity × canonical rate) and prices connected scope only. Unsupported scopes contribute nothing rather than a fabricated allowance.

ComponentAmountStatus
Construction cost (connected BOQ scope)EUR 16,122,379.38calculated
Land acquisitionEUR 4,440,000.00market-assumption
Consultants & design (arch/S/MEP, QS, PM)EUR 1,934,685.53assumed
Permits & authority feesEUR 644,895.18assumed
Site facilities & preliminariesEUR 1,612,237.94assumed
ContingencyEUR 1,289,790.35assumed
Testing & commissioningEUR 403,059.48assumed
Marketing & salesEUR 483,671.38assumed
Legal & insuranceEUR 322,447.59assumed
Financing costEUR 1,232,103.55derived
Total development costEUR 28,485,270.38derived

Construction cost per m² total GFA EUR 814.26 · per m² sellable EUR 1,433.10 · development cost per m² GFA EUR 1,438.65

Total development cost EUR 28,485,270.38 Construction (BOQ) — 56.6% (EUR 16,122,379.38) Land — 15.6% (EUR 4,440,000.00) Consultants & design (arch/S/MEP, QS, PM) — 6.8% (EUR 1,934,685.53) Permits & authority fees — 2.3% (EUR 644,895.18) Site facilities & preliminaries — 5.7% (EUR 1,612,237.94) Contingency — 4.5% (EUR 1,289,790.35) Testing & commissioning — 1.4% (EUR 403,059.48) Marketing & sales — 1.7% (EUR 483,671.38) Legal & insurance — 1.1% (EUR 322,447.59) Financing cost — 4.3% (EUR 1,232,103.55)

Quantity engine, BOQ & cost

20 engines contributed 50 consolidated materials → 50 BOQ items, 50 priced (100.0%), 0 unpriced. Every rate carries standing assumed and stays user-editable in the workflow.

ItemMaterialQuantity UnitRateAmount Source
5.1 Cut soil (export, loose) 25,500.00 m3 EUR 9.00/m3 EUR 229,500.00 earthwork/cut-fill-calculator/
2.1 Concrete (ready-mix) 9,413.03 m3 EUR 340.00/m3 EUR 3,200,431.56 concrete/footing-volume-calculator/
3.1 Steel rebar 504,089.76 kg EUR 2.10/kg EUR 1,058,588.50 rebar/weight-calculator/
6.1 Concrete blocks (incl. wastage) 37,320.00 each EUR 2.35/each EUR 87,702.00 masonry/quantity-calculator/
6.2 Masonry mortar 55.96 m3 EUR 145.00/m3 EUR 8,113.62 masonry/quantity-calculator/
10.1 Electrical cable 500.00 m EUR 26.00/m EUR 13,000.00 mep/electrical-calculator/
10.2 Distribution boards 60.00 each EUR 450.00/each EUR 27,000.00 mep/electrical-calculator/
10.3 MCBs 546.00 each EUR 48.00/each EUR 26,208.00 mep/electrical-calculator/
10.4 Distribution transformer 1.00 each EUR 14,500.00/each EUR 14,500.00 electrical/supply-calculator/
10.5 Standby generator 1.00 each EUR 26,000.00/each EUR 26,000.00 electrical/supply-calculator/
10.6 Main LV switchboards 2.00 each EUR 22,000.00/each EUR 44,000.00 electrical/supply-calculator/
10.7 LED luminaires 1,415.00 each EUR 145.00/each EUR 205,175.00 electrical/supply-calculator/
10.8 Emergency luminaires 900.00 each EUR 95.00/each EUR 85,500.00 electrical/supply-calculator/
11.1 Cold water pipe 450.00 m EUR 26.00/m EUR 11,700.00 mep/plumbing-calculator/
11.2 Hot water pipe 300.00 m EUR 32.00/m EUR 9,600.00 mep/plumbing-calculator/
11.3 Drainage pipe 360.00 m EUR 38.00/m EUR 13,680.00 mep/plumbing-calculator/
11.4 Water storage tanks 120.00 m3 EUR 650.00/m3 EUR 78,000.00 plumbing/systems-calculator/
11.5 Booster pump sets 2.00 each EUR 6,500.00/each EUR 13,000.00 plumbing/systems-calculator/
11.6 External stormwater drainage 108.00 m EUR 48.00/m EUR 5,184.00 plumbing/systems-calculator/
12.1 Air handling units 30.00 each EUR 14,000.00/each EUR 420,000.00 mep/mechanical-calculator/
12.2 Ductwork 9,900.00 m EUR 145.00/m EUR 1,435,500.00 mep/mechanical-calculator/
12.3 Diffusers 728.00 each EUR 110.00/each EUR 80,080.00 mep/mechanical-calculator/
13.1 Sprinkler heads 1,650.00 each EUR 78.00/each EUR 128,700.00 fire-safety/calculator/
13.2 Fire riser pipe 106.00 m EUR 95.00/m EUR 10,070.00 fire-safety/calculator/
13.3 Fire hydrants 4.00 each EUR 1,600.00/each EUR 6,400.00 fire-safety/calculator/
13.4 Fire extinguishers 66.00 each EUR 145.00/each EUR 9,570.00 fire-safety/calculator/
13.5 Fire alarm devices 364.00 each EUR 95.00/each EUR 34,580.00 fire-safety/calculator/
13.6 Fire water storage 179.00 m3 EUR 950.00/m3 EUR 170,050.00 fire/water-egress-calculator/
13.7 Fire pump sets 4.00 each EUR 38,000.00/each EUR 152,000.00 fire/water-egress-calculator/
13.8 Certified fire doors 66.00 each EUR 2,400.00/each EUR 158,400.00 fire/water-egress-calculator/
8.1 Plaster 506.25 m3 EUR 26.00/m3 EUR 13,162.50 finishes/calculator/
8.2 Paint 33,750.00 m2 EUR 14.00/m2 EUR 472,500.00 finishes/calculator/
8.3 Floor/wall tiles 3,375.00 m2 EUR 78.00/m2 EUR 263,250.00 finishes/calculator/
8.4 Flooring 11,250.00 m2 EUR 95.00/m2 EUR 1,068,750.00 finishes/calculator/
7.1 Glazing 4,764.98 m2 EUR 340.00/m2 EUR 1,620,093.20 finishes/calculator/
7.2 Facade panels (opaque) 1,301.32 m2 EUR 320.00/m2 EUR 416,422.40 envelope/calculator/
7.3 Roof waterproofing & finish 600.00 m2 EUR 145.00/m2 EUR 87,000.00 envelope/calculator/
14.1 External paving 1,440.00 m2 EUR 62.00/m2 EUR 89,280.00 site-infrastructure/calculator/
14.2 Drainage 120.00 m EUR 68.00/m EUR 8,160.00 site-infrastructure/calculator/
14.3 Landscaping 360.00 m2 EUR 48.00/m2 EUR 17,280.00 site-infrastructure/calculator/
14.4 Fencing 196.00 m EUR 95.00/m EUR 18,620.00 site-infrastructure/calculator/
14.5 Street lights 7.00 each EUR 850.00/each EUR 5,950.00 site-infrastructure/calculator/
15.1 Test points 350.00 each EUR 75.00/each EUR 26,250.00 testing/calculator/
15.2 Test instruments 14.00 each EUR 420.00/each EUR 5,880.00 testing/calculator/
4.1 Formwork (walls, columns, soffit) 31,482.00 m2 EUR 95.00/m2 EUR 2,990,790.00 structural/frame-calculator/
1.1 Waterproofing (basement tanking) 3,882.12 m2 EUR 75.00/m2 EUR 291,159.00 basement/works-calculator/
1.2 Sump pits with pumps 3.00 each EUR 5,200.00/each EUR 15,600.00 basement/works-calculator/
1.3 Basement ramp decks 94.50 m3 EUR 380.00/m3 EUR 35,910.00 basement/works-calculator/
9.1 Passenger lifts (traction) 2.00 each EUR 165,000.00/each EUR 330,000.00 vertical-transport/calculator/
9.2 Lift shaft construction 1,825.28 m2 EUR 320.00/m2 EUR 584,089.60 vertical-transport/calculator/

Construction cost (connected BOQ) EUR 16,122,379.38

Construction schedule

50 activities from quantities × labelled productivity; earliest-start pass over 521 days (25 months including preconstruction). No critical path, float, levelling or calendar.

Schedule — 50 activities, 25.0 monthsM0M1M2M3M4M5M6M7M8M9M10M11M12M13M14M15M16M17M18 Bulk excavation (export) 64d Concrete works (in-situ) 269d Reinforcement fixing 101d Blockwork partitions 47d Blockwork mortar beds 14d Electrical cable installation 3d Distribution board installation 15d MCB installation 11d Cold water pipe installation 15d Hot water pipe installation 12d Drainage pipe installation 11d AHU installation 15d Ductwork installation 99d Diffuser installation 19d Sprinkler head installation 17d Fire riser installation 6d Fire hydrant installation 2d Fire extinguisher installation 4d Fire alarm device installation 13d Plaster application 11d Painting 169d Tiling 85d Glazing installation 159d Flooring installation 188d External paving 15d Drainage installation 4d Landscaping 8d Fencing installation 5d Street light installation 2d Testing 7d Commissioning 3d Formwork erection & striking 350d Basement tanking & waterproofing 87d Sump pits & pumps 3d Basement ramp construction 16d Lift installation & commissioning 2d Lift shaft construction 153d Facade panel installation 38d Roof waterproofing 9d Transformer installation 1d Generator installation & load bank test 1d Main switchboard installation 2d Luminaire installation 32d Emergency luminaire installation 15d Water tank installation 120d Booster pump set installation 2d External stormwater installation 5d Fire water tank construction 45d Fire pump set installation & testing 4d Fire door installation 9d
Activities (50)
ActivityPackageStartEndDays
Bulk excavation (export)substructure 063 64d
Concrete works (in-situ)superstructure 64332 269d
Reinforcement fixingsuperstructure 64164 101d
Blockwork partitionsenvelope 333379 47d
Blockwork mortar bedsenvelope 333346 14d
Electrical cable installationmep-fit 380382 3d
Distribution board installationmep-fit 380394 15d
MCB installationmep-fit 380390 11d
Cold water pipe installationmep-fit 380394 15d
Hot water pipe installationmep-fit 380391 12d
Drainage pipe installationmep-fit 380390 11d
AHU installationmep-fit 380394 15d
Ductwork installationmep-fit 380478 99d
Diffuser installationmep-fit 380398 19d
Sprinkler head installationmep-fit 380396 17d
Fire riser installationmep-fit 380385 6d
Fire hydrant installationmep-fit 380381 2d
Fire extinguisher installationmep-fit 380383 4d
Fire alarm device installationmep-fit 380392 13d
Plaster applicationenvelope 333343 11d
Paintingenvelope 333501 169d
Tilingenvelope 333417 85d
Glazing installationenvelope 333491 159d
Flooring installationenvelope 333520 188d
External pavinggeneral 385399 15d
Drainage installationgeneral 385388 4d
Landscapinggeneral 385392 8d
Fencing installationgeneral 385389 5d
Street light installationgeneral 385386 2d
Testinggeneral 385391 7d
Commissioninggeneral 385387 3d
Formwork erection & strikingsuperstructure 64413 350d
Basement tanking & waterproofingsubstructure 086 87d
Sump pits & pumpssubstructure 02 3d
Basement ramp constructionsubstructure 015 16d
Lift installation & commissioningvertical-transport 383384 2d
Lift shaft constructionsuperstructure 64216 153d
Facade panel installationenvelope 333370 38d
Roof waterproofingenvelope 333341 9d
Transformer installationmep-fit 380380 1d
Generator installation & load bank testmep-fit 380380 1d
Main switchboard installationmep-fit 380381 2d
Luminaire installationmep-fit 380411 32d
Emergency luminaire installationmep-fit 380394 15d
Water tank installationmep-fit 380499 120d
Booster pump set installationmep-fit 380381 2d
External stormwater installationsubstructure 04 5d
Fire water tank constructionsubstructure 044 45d
Fire pump set installation & testingmep-fit 380383 4d
Fire door installationenvelope 333341 9d

Procurement

15 packages from BOQ materials × lead times × schedule dates. Every connected item has a date.

PackageItemsEarliest requiredOrder byCost
Earthworks — excavation, disposal & fill imports 1 2026-10-19 2026-10-14 EUR 229,500.00
Substructure & basement — slab, walls, tanking, sumps, ramp 3 2026-10-19 2026-10-05 EUR 342,669.00
Ready-mix concrete & placements 1 2026-12-22 2026-12-01 EUR 3,200,431.56
Reinforcement bars & cages 1 2026-12-22 2026-12-08 EUR 1,058,588.50
Formwork & soffit decks 1 2026-12-22 2026-12-01 EUR 2,990,790.00
Masonry & mortar supply 2 2027-09-17 2027-09-10 EUR 95,815.62
Envelope — facade, glazing & roofing 3 2027-09-17 2027-08-03 EUR 2,123,515.60
Internal finishes 4 2027-09-17 2027-09-10 EUR 1,817,662.50
Vertical transportation — lifts & shafts 2 2026-12-22 2026-09-23 EUR 914,089.60
MEP electrical — supply, cable, DBs, luminaires 8 2027-11-03 2027-10-04 EUR 441,383.00
MEP plumbing — pipework, tanks, pumps, stormwater 6 2026-10-19 2026-10-09 EUR 131,164.00
MEP mechanical — AHUs, ductwork, plant 3 2027-11-03 2027-09-19 EUR 1,935,580.00
Fire & life safety — suppression, detection, egress 8 2026-10-19 2026-09-04 EUR 669,770.00
Site infrastructure & external works 5 2027-11-08 2027-11-03 EUR 139,290.00
Testing & commissioning 2 2027-11-08 2027-11-05 EUR 32,130.00
Procurement — order window (order by → required by), package cost Earthworks — excavation, disposal & fill imports EUR 229,500 Substructure & basement — slab, walls, tanking, sumps, ramp EUR 342,669 Ready-mix concrete & placements EUR 3,200,432 Reinforcement bars & cages EUR 1,058,589 Formwork & soffit decks EUR 2,990,790 Masonry & mortar supply EUR 95,816 Envelope — facade, glazing & roofing EUR 2,123,516 Internal finishes EUR 1,817,663 Vertical transportation — lifts & shafts EUR 914,090 MEP electrical — supply, cable, DBs, luminaires EUR 441,383 MEP plumbing — pipework, tanks, pumps, stormwater EUR 131,164 MEP mechanical — AHUs, ductwork, plant EUR 1,935,580 Fire & life safety — suppression, detection, egress EUR 669,770 Site infrastructure & external works EUR 139,290 Testing & commissioning EUR 32,130

Cash flow & financing

Monthly cash flow derived from cost × schedule over 25 months to Apr 2028. Financing 60% debt / 40% equity at 6.0% simple, computed on the pre-financing cost so it is never circular.

ParameterValue
Pre-financing costEUR 27,253,166.82
Loan amountEUR 16,351,900.09
EquityEUR 10,901,266.73
Total interestEUR 1,232,103.55
Peak loan outstandingEUR 16,351,900.07
Peak equity callEUR 10,901,266.72
Peak cash requirementEUR 27,253,166.79
EUR 0 EUR 6,813,292 EUR 13,626,583 EUR 20,439,875 EUR 27,253,167peak EUR 27,253,167months (incl. preconstruction)— cumulative

Scenario engine

Scenarios are override factors fed back through the same model builders. Every outcome is recomputed — none is display-adjusted.

Base case

Reference assumptions, no override.

Delay
0 mo
TDC
EUR 28,485,270.38
Profit
EUR 6,872,229.62
Margin
19.4%

Downside

Land +20%, construction cost +15%, sales price −10%, completion delayed 6 months.

Delay
6 mo
TDC
EUR 33,563,182.49
Profit
EUR -1,741,432.49
Margin
-5.5%

Upside

Land −10%, construction cost −8%, sales price +10%, on time.

Delay
0 mo
TDC
EUR 26,111,654.74
Profit
EUR 12,781,595.26
Margin
32.9%
Base caseDownsideUpsideEUR 0EUR 19,446,625EUR 38,893,250 Base case: EUR 35,357,500 Downside: EUR 31,821,750 Upside: EUR 38,893,250 Revenue Base case: EUR 28,485,270 Downside: EUR 33,563,182 Upside: EUR 26,111,655 TDC Base case: EUR 6,872,230 Downside: EUR -1,741,432 Upside: EUR 12,781,595 Profit

Sales, revenue & developer profitability

Revenue = unit program × declared market prices. Prices are assumptions, not market-verified data. Return on development cost is not ROI — this model contains no IRR or NPV.

MeasureValue
Gross revenueEUR 35,357,500.00
Total development costEUR 28,485,270.38
Profit (pre-tax)EUR 6,872,229.62
Gross margin19.4%
Return on development cost24.1%
Profit per m² sellableEUR 610.86
Break-even priceEUR 2,532.02/m²
Break-even area9,063 m²
Achieved priceEUR 3,142.89/m²
Gross revenue EUR 35,357,500 — including parking Studio EUR 5,145,000 1 Bedroom EUR 9,240,000 2 Bedroom EUR 7,560,000 3 Bedroom EUR 11,182,500 Penthouse EUR 1,530,000 Parking EUR 700,000

Model integrity & coverage

The model is machine-checked against its own invariants before anything is rendered. Diagnostics are shown, never hidden.

CONSISTENT — all scope, area, unit, BOQ, rate, cost, financing, revenue, profit, schedule and traceability invariants hold.

Coverage — 17/30 disciplines available (57%) Land & site Assumption-only Survey & geotechnical Not modelled Development feasibility Connected Areas & unit program Connected Architecture — unit program Partial Earthworks & excavation Engineering-modelled Substructure & basement Engineering-modelled Structural frame Engineering-modelled Envelope, facade & roofing Screening-level Electrical — supply & distribution Screening-level Plumbing & drainage Screening-level Mechanical — HVAC Screening-level Fire & life safety Screening-level Vertical transportation Screening-level Site & external works Engineering-modelled Quantity engine Connected Bill of quantities Connected Rate model Connected Construction cost Connected Construction schedule Connected Resources & labour Assumption-only Procurement Connected Cash flow Connected Financing Connected Testing & commissioning Screening-level Handover Not modelled Operation & OPEX Not modelled Sales & revenue Connected Developer profitability Connected Scenario engine Connected

Traceability

Reverse trace: every BOQ item resolves to its producing calculator, revision and record (100% complete). Forward trace: scope → engine input derivations below.

ItemMaterialCalculatorRevisionRecord
5.1 cut-soil earthwork/cut-fill-calculator/ …v-ye5hb8 demo-cut-fill:exportVolumeLooseM3:rev-ye5hb8
2.1 concrete concrete/footing-volume-calculator/ …v-wu0w0f demo-footing-volume:readyMixVolumeM3:rev-wu0w0f
3.1 rebar rebar/weight-calculator/ …v-jg78yg demo-rebar-weight:totalWeightKg:rev-jg78yg
6.1 masonry-blocks masonry/quantity-calculator/ …ev-58v7f demo-masonry-quantity:blockCount:rev-58v7f
6.2 masonry-mortar masonry/quantity-calculator/ …ev-58v7f demo-masonry-quantity:mortarVolumeM3:rev-58v7f
10.1 mep-cable mep/electrical-calculator/ …-17yp9u4 demo-mep-electrical:mainCableLengthM:rev-17yp9u4
10.2 mep-db mep/electrical-calculator/ …-17yp9u4 demo-mep-electrical:distributionBoards:rev-17yp9u4
10.3 mep-mcb mep/electrical-calculator/ …-17yp9u4 demo-mep-electrical:mcbCount:rev-17yp9u4
10.4 mep-transformer electrical/supply-calculator/ …-1yywphx demo-electrical-supply:transformerCount:rev-1yywphx
10.5 mep-generator electrical/supply-calculator/ …-1yywphx demo-electrical-supply:generatorCount:rev-1yywphx
10.6 mep-switchboard electrical/supply-calculator/ …-1yywphx demo-electrical-supply:mainSwitchboardCount:rev-1yywphx
10.7 mep-luminaire electrical/supply-calculator/ …-1yywphx demo-electrical-supply:luminaireCount:rev-1yywphx
10.8 mep-emergency-light electrical/supply-calculator/ …-1yywphx demo-electrical-supply:emergencyLuminaireCount:rev-1yywphx
11.1 mep-cw-pipe mep/plumbing-calculator/ …-1ncc7dh demo-mep-plumbing:coldWaterPipeM:rev-1ncc7dh
11.2 mep-hw-pipe mep/plumbing-calculator/ …-1ncc7dh demo-mep-plumbing:hotWaterPipeM:rev-1ncc7dh
11.3 mep-drain-pipe mep/plumbing-calculator/ …-1ncc7dh demo-mep-plumbing:drainagePipeM:rev-1ncc7dh
11.4 mep-tank plumbing/systems-calculator/ …v-xv0gx2 demo-plumbing-systems:storageVolumeM3:rev-xv0gx2
11.5 mep-pump plumbing/systems-calculator/ …v-xv0gx2 demo-plumbing-systems:boosterPumpSetCount:rev-xv0gx2
11.6 mep-stormwater plumbing/systems-calculator/ …v-xv0gx2 demo-plumbing-systems:stormWaterPipeLengthM:rev-xv0gx2
12.1 mep-ahu mep/mechanical-calculator/ …v-wamxxn demo-mep-mechanical:ahuCount:rev-wamxxn
12.2 mep-duct mep/mechanical-calculator/ …v-wamxxn demo-mep-mechanical:ductLengthM:rev-wamxxn
12.3 mep-diffuser mep/mechanical-calculator/ …v-wamxxn demo-mep-mechanical:diffuserCount:rev-wamxxn
13.1 fire-sprinkler-head fire-safety/calculator/ …-1pir0r4 demo-fire-safety:sprinklerHeads:rev-1pir0r4
13.2 fire-riser fire-safety/calculator/ …-1pir0r4 demo-fire-safety:riserLengthM:rev-1pir0r4
13.3 fire-hydrant fire-safety/calculator/ …-1pir0r4 demo-fire-safety:hydrantCount:rev-1pir0r4
13.4 fire-extinguisher fire-safety/calculator/ …-1pir0r4 demo-fire-safety:extinguisherCount:rev-1pir0r4
13.5 fire-alarm fire-safety/calculator/ …-1pir0r4 demo-fire-safety:alarmDeviceCount:rev-1pir0r4
13.6 fire-tank fire/water-egress-calculator/ …-1yi792y demo-fire-water-egress:fireTankVolumeM3:rev-1yi792y
13.7 fire-pump fire/water-egress-calculator/ …-1yi792y demo-fire-water-egress:firePumpCount:rev-1yi792y
13.8 fire-door fire/water-egress-calculator/ …-1yi792y demo-fire-water-egress:fireDoorCount:rev-1yi792y
8.1 finish-plaster finishes/calculator/ …-1cow7w5 demo-finishes-facades:plasterVolumeM3:rev-1cow7w5
8.2 finish-paint finishes/calculator/ …-1cow7w5 demo-finishes-facades:paintAreaM2:rev-1cow7w5
8.3 finish-tile finishes/calculator/ …-1cow7w5 demo-finishes-facades:tileAreaM2:rev-1cow7w5
8.4 finish-flooring finishes/calculator/ …-1cow7w5 demo-finishes-facades:flooringAreaM2:rev-1cow7w5
7.1 finish-glazing finishes/calculator/ …-1cow7w5 demo-finishes-facades:glazingAreaM2:rev-1cow7w5
7.2 facade-panel envelope/calculator/ …v-gmfj6a demo-envelope:opaquePanelAreaM2:rev-gmfj6a
7.3 roofing-membrane envelope/calculator/ …v-gmfj6a demo-envelope:roofAreaM2:rev-gmfj6a
14.1 site-paving site-infrastructure/calculator/ …v-xlhgm9 demo-site-infrastructure:pavingAreaM2:rev-xlhgm9
14.2 site-drainage site-infrastructure/calculator/ …v-xlhgm9 demo-site-infrastructure:drainageLengthM:rev-xlhgm9
14.3 site-landscape site-infrastructure/calculator/ …v-xlhgm9 demo-site-infrastructure:landscapingAreaM2:rev-xlhgm9
14.4 site-fencing site-infrastructure/calculator/ …v-xlhgm9 demo-site-infrastructure:fencingLengthM:rev-xlhgm9
14.5 site-lighting site-infrastructure/calculator/ …v-xlhgm9 demo-site-infrastructure:streetLightCount:rev-xlhgm9
15.1 test-points testing/calculator/ …v-gmx4px demo-testing-commissioning:totalTestPoints:rev-gmx4px
15.2 test-instrument testing/calculator/ …v-gmx4px demo-testing-commissioning:instrumentCount:rev-gmx4px
4.1 formwork structural/frame-calculator/ …v-zotucp demo-structural-frame:totalFormworkM2:rev-zotucp
1.1 waterproofing basement/works-calculator/ …v-jdv1xm demo-basement-works:waterproofingAreaM2:rev-jdv1xm
1.2 sump basement/works-calculator/ …v-jdv1xm demo-basement-works:sumpCount:rev-jdv1xm
1.3 basement-ramp basement/works-calculator/ …v-jdv1xm demo-basement-works:rampConcreteM3:rev-jdv1xm
9.1 lift-elevator vertical-transport/calculator/ …-13ewe4s demo-vertical-transport:liftCount:rev-13ewe4s
9.2 lift-shaft vertical-transport/calculator/ …-13ewe4s demo-vertical-transport:liftShaftWallAreaM2:rev-13ewe4s
Forward derivations (project scope → engineering inputs)
  • Identity from scope: 30 storeys × 600 m² = 18000 m² above-grade GFA; 3 basements × 600 m² = 1800 m² basement GFA; total GFA 19800 m² over 33 levels.
  • Unit program from scope: 182 units, 11250 m² sellable, 2376 m² service/core, 4374 m² common (GFA − sellable − parking − service/core).
  • Building footprint 600 m² at a 2.5:1 aspect ratio → perimeter 108 m (used for facade and hydrant layout, never the land perimeter).
  • Cut = footprint 600 m² × basements 3 × 4 m per basement × working-space/slope factor 3 = 21600 m³. Fill = cut ÷ 18 reused around footings = 1200 m³ (demonstration derivation).
  • Columns = 24 per storey (core + perimeter) × 30 storeys = 720 (demonstration derivation).
  • Slabs = 31 (30 storeys + roof) of 30 m × 20 m footprint (600 m² divided at 30 m length, demonstration derivation).
  • Rebar bar schedule = slab area 18600 m² ÷ 1.0333 m² per bar ≈ 18000 bars (demonstration schedule — NOT a structural design).
  • Partitions = 1200 m run (40 m per storey × 30, demonstration) with 540 m² openings (18 m² per storey, demonstration derivation).
  • Structural frame = 4 beam lines/floor × 30 m × 33 levels (0.4 × 0.65 m) + core/shear walls 90 m² × 0.3 m × 33 levels + 2 stair flights/level (3.2 m rise @ 0.28 m going, 1.4 m wide). Screening-level, not a design.
  • Basement works over 3 levels: base slab 600 m² × 0.6 m, retaining walls 108 m × 3.2 m × 0.35 m, columns at 1 per 60 m², grade beams 0.35 m/m², ramp 120 m², tanking + 1 sump per level. Derived from the same footprint and perimeter as the building.
  • Lifts sized on 182 units × 2.4 persons × 1.1 population factor, 5-minute handling interval, 13-person cars, 110 s cycle; shafts over 99 m.
  • Facade = perimeter 108 m × 30 storeys, 60% glazed / 40% opaque panel; parapet 1.2 m; roof 100% of the 600 m² plate. Facade is geometric, not a share of sellable area.
  • mep electrical = TOTAL GFA 19800 m² (basements included) × 50 W/m² = 990.0 kW connected; diversity 60% → 594.0 kVA max demand (demonstration).
  • Transformer sized on the 594.0 kVA computed max demand + 15% allowance, rounded up to a standard rating; generator on 35% critical load; luminaires at 14 m² each and emergency luminaires at 22 m² each over 19800 m².
  • mep plumbing = 182 units × 4 FU/unit = 728 FU; cold water 15 m/floor, hot 10 m/floor, drainage 12 m/floor (demonstration).
  • Plumbing demand = 182 units × 2.4 persons × 180 L/person/day → storage sized on a 12-hour drawdown (min 120 m³); booster set on 12 L/s at 58 m head; stormwater from roof 600 m² + hardstanding at 180 L/s/ha.
  • mep mechanical = TOTAL GFA 19800 m² × 3 m × 2 ACH = 118,800 m³/h air; cooling 1980 kW (demonstration).
  • fire safety = TOTAL GFA 19800 m² (basements included) ÷ 12 m²/head = 1650 sprinkler heads; riser 96 m; hydrants every 30 m along the 108 m building perimeter.
  • Fire water & egress = occupant load at 12.5 m²/person over 19800 m²; design flow 0.15 L/min/m² over 60 min, tank floored at 150 m³; 2 pump zones (duty + standby each); 2 escape stairs serving 33 levels with rated doors to every served floor.
  • Finishes = 11250 m² sellable (from the unit program) × 3 for wall surface = 33750 m² internal wall area; plaster 15 mm = 506.3 m³; tiles 30%, flooring 11250 m² (demonstration).
  • Site infra = site 2400 m² (from the scope) − footprint 600 m² − landscaping 360 m² = 1440 m² paving; fencing ~196 m (demonstration).
  • testing = 7 systems × 50 pts = 350 test points; 7 systems × 5 days = 35 commissioning days (demonstration).

Datasets & exports