EngiMetric Arena / Spot the Error

Review this concrete order: wastage counted twice

  • Spot the Error
  • Construction & QS
  • foundation
Competency Quantitative reasoning primary

What you should take away: Recognise that a percentage allowance is applied once to the measured quantity, not compounded onto an already adjusted total.

The situation

What is happening

A ground slab is 12 m long, 8 m wide and 250 mm thick. The quantity surveyor calculated 24 m3, added 5 % wastage, then added a second 5 % for pump losses and issued an order for 26.46 m3. Review the order before it is placed.

Given

Scenario values with units
QuantityValueUnitNote
Slab length 12 m Measured plan dimension.
Slab width 8 m Measured plan dimension.
Slab thickness 250 mm Design thickness.
Wastage allowance 5 % The project allowance for spillage and loss.
Issued order 26.46 m3 What the review has to check.

Assumptions this challenge makes

  • The slab is a simple rectangle with no openings or thickened edges.
  • Wastage is a single project allowance, not a separate allowance per trade.

Your call

Your answer

Which finding is the defensible review conclusion?

What this challenge does not establish

  • The slab is treated as a plain rectangle; openings, chamfers and thickened edges would change the measured volume.
  • The 5 % allowance is taken as the project allowance. A different measured loss would change the correct order.
  • No allowance is made for pump priming, washout or rejected loads beyond the stated percentage.