Staircase concrete volume and how it splits up
Waist slab, steps and landing as separate volumes, and why the pour is usually smaller than people expect.
The engineering question
A staircase needs formwork more than it needs concrete. How do you get the volume, and what drives the shuttering quantity?
Worked example
The figures below were produced by running the Staircase Concrete Volume Calculator with the same inputs — during the build, from its authoritative engine.
| Total concrete volume | 1.404 m³ |
|---|---|
| Waist slab volume | 0.7608 m³ |
| Steps volume | 0.4704 m³ |
| Landing volume | 0.1728 m³ |
| Sloping slab length | 5.283 m |
| Flight rise | 2.8 m |
| Flight going | 4.48 m |
| Assessment | Flight rise 2.80 m over 4.48 m going; slab ≈ 5.3 m long → ≈ 1.40 m³ of concrete (waist 0.76 + steps 0.47 + landing 0.17). |
- The sloping slab length is the flight rise and going taken together.
- Waist volume is length × thickness × width; steps add a triangular prism per riser.
- The landing is added separately, and often at a different thickness.
Sanity check
16 risers at 175 mm rises 2.8 m and goes 4.48 m. If the geometry looks wrong, check that treads were not entered as clear opening rather than going.
Tools for this problem
These are the EngiMetric calculators that compute the numbers in this topic. Each one shows its formula, its units and its limits rather than returning a bare result.
References & standards
- BS 8500-2 — construction of reinforced concrete stairs
- EN 1992-1-1 — design of concrete staircases
Related problems
Taking off concrete volumes without mis-ordering the pour
Where concrete volume actually goes — including the parts that are habitually forgotten — and how wastage and batching affect the order.
Also: Civil & Structural
Designing formwork for the pressure of fresh concrete, not hardened concrete
Why formwork is designed for placement rate and temperature rather than the weight of the finished slab, and where the hydrostatic cap applies.
Also: Civil & Structural