Engineering Application

Bulk excavation for foundations and basements, trenching for utilities, cut-and-fill earth balance on sites, and hauling of imported/exported material. Volume calculations must apply swell (loose) and shrinkage (compacted) factors to bank cubic metres.

Key Parameters

Parameter Unit
Bucket / heaped capacity
Cycle time min
Swell / shrinkage factor %
Production rate m³/h

Related Engineering Tools

Construction Live Tool

Trench Excavation & Bedding Calculator

Calculate trench excavation volume, pipe displacement, bedding material quantity, and backfill volumes.

V_trench = A × L · Backfill = V_trench − V_pipe − V_bedding
Construction Live Tool

Earthwork Cut and Fill Calculator

Estimate site earth movement balance and bulk haulage volumes with swell and shrinkage factors.

Net = ΣCut − ΣFill (bank m³) · Export = Net × (1 + swell/100) · Import = −Net × (1 + shrink/100)